Although we had initially arranged for our mechanicals contractor, Todd Hawkes, to line up an electrician, with the sudden unexpected arrival of the Battle Creek building crew, we had to go to plan B. We needed to begin the wiring as soon as possible as it has to be done while the log cabin is being built, unlike a standard home construction, where you can run the wire after the framing is complete. Fortunately, Mr. Lipham had an electrician that he’s worked with previously who happened to be available and was willing to drive up from Alabama to help us out. Within moments of meeting Andy, we were thrilled to have him join our team and it soon became clear that he knew a little more about building log homes than just running wire.
- Andy and Mr. Lipham discuss the supplies we will need for the wiring
- haha…no one warned Andy that I’d be recording his every move
- drilling holes in the basement for the wiring
- running the wires
The wiring having been started and framing of the rafters done, things were running pretty smoothly until, in the course of inventorying the timber that was still left, three large lamibeams were discovered. Since all the heavy timber beams were in place at this point, the crew went back to review the blue prints to figure out where they should have been. It was at this point that it was discovered that there were two sets of plans on site that were being used. The difference between the two, one being an engineer set, showing lamibeams in place of the heavy timber beams that run the length of both the ceiling of the first floor as well as the roof peak. Since it was the engineered plans that had been submitted for the building permit, that meant in order for us to pass inspection the solid timbers that were already in place would have to be switched out for the lamibeams which are slightly stronger.
While the crew broke for lunch, Dave, Mr. Lipham, and José discussed what needed to be done.
- the crew on their lunch break
- Andy and Mr. Lipham join the rest of the crew
- Miguel shows us the day’s catch
- Bingo checks out the fish
- “hmmm, I wonder if anyone would notice I took just a bite”
- Bingo tires of the fish and makes himsefl at home in my vacant chair
A bit of a set back to say the least, but Mr. Lipham, José and our fabulous crew took it in stride and, their main concern being to do things right, wasted no time in switching them out. That meant un-building much of the roof and first floor ceiling structure that was already in place.
- Dave, Mr. Lipham and José
- putting in temporary structure to support the roof rafters while they replace the timbers
- unbuilding the roof timber
- our building crew busy at work on the roof system
- side view of the temporary boards the crew has placed
- the forsaken lamibeams
- up goes a lamibeam
- must be cut to fit
- removing the solid timber beam
- success!
- now to lift the lamibeam into place
- first one in place!
- and the second one
- re-nailing the rafters
- both beams successfully replaced!
–
Having successfully replaced the timbers on the roof peak, the crew switched their attention inside to the three beams that run the length of the first floor ceiling.
- removing the temporary flooring from the second floor
- solid timber in the kitchen/dining area is unattached
- un-attaching the master bedroom rafters
- removing the solid timber beam
- bringing in the lamibeam
- heavy, very heavy…
- jokes log craftsmen play on one another- drop one end of the heavy timber leaving your buddy to carry the entire thing
- Mr. Lipham steps in to lend a hand
- even Andy pitches in to help
- just a little higher guys!
- re-attaching the rafters
- newly replaced lamibean
- the lamibeams, though stronger than the solid timber, are slightly smaller so shims were placed to fill the gap
Although it put the crew a full day behind, we were all relieved that they were able to successfully replace all the beams with relatively few complications. Hopefully that will be the last little hiccup during the building process!
Recent Comments