and then there’s the wiring issue….

I imagine that a certain amount of frustration is to be expected anytime you take on a large construction project. With that in mind, aside from a few hiccups along the way, we consider ourselves relatively lucky that most things have gone smoothly thus far. That is, if we don’t consider the wiring issue.

We were initially referred to a local company, McCray Electric, when we first began to put our plans for building in motion and scheduled an appointment to meet with them back in September. Completely clueless as to how to go about lighting our cabin or where we would need to place all of the outlets, we took our cabin plans in and met with them to discuss various options and ideas, feeling very confident when we left our meeting that they would do a fantastic job. They said they had wired other log cabins in the past and seemed well aware of how to best go about the job, bringing up things we’d never even thought of. After discussing the project in length, we were told that they would go over the plans a bit more thoroughly in the coming week and then get back to us with a price quote and give us a complete plan for wiring our new cabin. Several weeks went by and several phone calls were made, each time we were told they would get back to us with a quote, “tomorrow”.  It’s now February and we’re still waiting for them to call “tomorrow” with their price quote!

In the meantime, construction began and we needed an electrician to go ahead and start wiring as the logs were being laid. At Mr. Lipham’s recommendation, we agreed for him to bring up his electrician from Alabama to do the job. We absolutely loved Andy (who turned out to be Mr. Lipham’s son for those of you who haven’t been following all along) and found him to be much fun to have on the site. Clearly he was knowledgable not only as far as the wiring, but in all areas of building a log home. The problem was, after wiring half the cabin, he had to return home to Alabama and the rest of the wiring was left to another member of Mr. Lipham’s crew who had been helping Andy wire the basement and first floor.  We soon began to suspect that the only training Raymond had in running wire was the two days he worked with Andy before he had gone back home to Alabama. The idea was that Andy was going to return to finish up what Raymond couldn’t do at the same time Mr. Lipham returned to finish up the few construction projects that were left undone when the building crew had left. Unfortunately, circumstances did not allow for them to return when they had initially planned and, as we needed to move forward with construction, we eventually had to make other arrangements to get the work completed.

Having little luck in finding an electrician that would come in to finish what Andy had left undone, fix the mess that Raymond had made, as well as to sort through the quagmire of unmarked wires that were running haphazardly throughout the three floors, Dave finally decided he’d take on the project himself. Having a father who is an electrician, as well as having previously wired a house that he had renovated in Richmond’s historic Church Hill, he was no stranger to the task. He’d just been trying to avoid it. He has now spent the last three weeks sorting out the mess of unmarked wires, starting by first by going wire by wire, attaching a 9volt battery on one end and a current detector on the other,  painstakingly going through the entire cabin trying to figure out what runs where and labeling each with a sharpy as he goes along. He has also confirmed what we had feared- that everything Raymond had run on the second floor, as well as much of the main floor, has to be redone.

While we’ve been working on the wiring, Todd Hawkes and crew have started putting the stone on the chimney….AWESOME!

Gentry Well Works have been back as well…

Categories: Follow the adventure as we build our log cabin | Tags: , , , , , , | 1 Comment

drilling the well…we have water at last!

Okay, so we don’t actually have water in the cabin yet, but, thanks to Gentry Well Works Inc., who came out this week and drilled our well, we’re that much closer to running water. Hooray! The septic system should go in next week so it’s only a matter of time now…

Categories: Follow the adventure as we build our log cabin | Tags: , , , , | Leave a comment

front porch stair rails, check… fireplace stone, check…

We had started working on the handrails for the front porch stairs the day we finished the interior of the fireplace but ran out of time so that was the first on our agenda to complete this past weekend.

Next, we set the log mantel supports in place so Todd Hawkes and his crew could begin putting the stone around the fireplace.

After looking through countless samples of rock, we had settled on using Eldorado stone veneer in Shadow Rock Willow and were extremely pleased with our choice! Our initial reason for using a wood burning fireplace insert and stone veneer was to cut back on cost a bit but in the end we could have done a full masonry fireplace for what we ended up paying!

Categories: Follow the adventure as we build our log cabin | Tags: , , , , , , | Leave a comment

winter hits Colemans Lake…what a perfect time to test out the fireplace!

This week’s snow east coast snow storm and frigid temperatures did not leave Colemans Lake untouched. When we arrived Sunday morning, we found snow still covering much of the ground and the lake and dam area filled with a lovely array of ice sculptures.

We spent the morning finishing the inside of the fireplace and were finally able to test it out. We couldn’t have picked a more perfect day for our first fire!

Categories: Follow the adventure as we build our log cabin | Tags: , , | Leave a comment

in which we finally build front porch stairs…no more entering by ladder, yea!

Until this past weekend, in order to enter the cabin through the front door, we’ve had to use a ladder to climb up onto the front porch. Not a big deal but a bit tiresome when you’re carrying tools and various supplies in and out of the place. Finally, after three months of doing just that, we took on the task of building front porch stairs.

Once again, when we arrived at the lake, the temperature was below freezing and the ground was covered in inch and a half ice crystals that seem to grow upwards out of the ground every night.  Much fun to step on as they create a very satisfying crunch as you walk…not so much fun once the sun melts them as the melted ice turns the entire work site into a giant pit of mud.  Dave hates mud.  It makes him grumpy. Especially when his tools fall into it.

Dave wasted no time in setting up his work station and getting to the task at hand. After digging two holes and placing cement blocks in each to support the stairs, using heavy timber and careful to stay out of the mud, he whipped us out a set of stairs.

With only a short period of daylight left, we decided to wait and finish the hand rails next week and to move on to finishing the trim around the doors in the back. While working on the trim around the master bedroom door, I looked up to discover a visitor checking out our bedroom…stairs up less than a day and we already had a guest come to check them out! It was an adorable little black and brown beagle mix, who, although very curious, was unfortunately way too skittish to let me come near it.  Note to self, bring dog treats next weekend.  🙂

And last on the list of tasks for the day, was to find a log the right size to use for making supports for the fire place mantel.

IMG_5816

Dave uses the chainsaw to cut two piece of log to make supports for the fireplace mantel

Categories: Follow the adventure as we build our log cabin | Tags: , , , | Leave a comment

framing up the fireplace wall and hearth

Another crazy weekend, weather wise.  Saturday started with heavy fog that was just beginning to lift as we got to the lake.  It was already warm and humid out when we arrived and supposed to get up into the 70s, but not so inside the cabin.  As soon as we opened the front door, we were hit by an icy draft as the cold air from inside the cabin rushed out.

Undeterred from the icy inside temps, Dave started up the generator, turned on the heater, and went to town building the fireplace wall.

And, incase you were wondering what our place looks like from above, Todd Hawkes just sent us this photo… Thanks Todd!!!

Image

The Coleman Cabin and Colemans Lake as seen from above

Categories: Follow the adventure as we build our log cabin | Tags: , , , , , , , | Leave a comment

finishing the dormers, closing in the chimney, putting in the basement windows and starting the roof

Okay, so I got a little behind with my bloggin’ over the holidays…bear with me, a lot has been happening so this is going to be a long one!

When the JM Logcraftsman crew left on Thanksgiving Day, there were still a few things left unfinished.  They had run out of log siding for the second time so were unable to finish one of the dormers and, therefore, unable to stain them as well. In addition, the original basement windows that had been delivered with the rest of the kit ended up being the wrong size so new windows had to be ordered but had not yet arrived before the crew left. The wiring on the second floor was also incomplete and that which had been done was done incorrectly as, once Andy left, it had been left to be completed by one of the crew members who was unfamiliar with wiring. The original plan was for Mr. Lipham, Andy and one other crew member to return the first week in December to finish these three things, as well as to finish staining the outside of the cabin. The first week turned into the second week, which then turned into no communication from anyone as to when they might be back.

Granted, this was all during the holiday season and Mr. Lipham had also taken on building another cabin in Arkansas so I have no doubt that he and Andy both were being pulled in all different directions.  Having said that, regardless of what is happening on their end, the fact of the matter is that our place is still unfinished and we need to move forward.  Our local contractor, Todd Hawkes, had lined up people to start the plumbing, the HVAC and the roof and they were all ready to get started. Unfortunately, the dormers in particular had to be completed before the roof could be put on so, still hearing no date for Mr. Lipham to return, Dave arranged with Battle Creek to have the log siding and basement windows to be delivered directly to us so we could move forward.

Finishing the dormers

Although the log siding had yet to arrive, we went down the weekend before Christmas to start staining the dormers in the front so that the roofers could at least start on that side.  Dave also wanted to change out the trim on the arched window over the entrance as, on closer inspection, we realized it was less than spectacular to say the least.  By the time we finished the front dormers and had stained what we could in the back, the siding arrived so the following weekend we were able to get that up and finish staining the last dormer so the roofers could begin.

Putting in the basement windows

Meanwhile, the new basement windows had also arrived.  Thankfully, they proved to be relatively simple to put in and made a huge difference in the amount of light in the basement once they were in.

Putting in the fireplace/chimney insert

One of our next goals is to get the fireplace in working order so we can warm up the inside of the cabin to make working on the inside a little more pleasant during these coming winter months. Over the past few weekends we’ve been making progress and were finally successful this past weekend in getting the last of the chimney inserts in place and closing up the chimney.

HVAC & Plumbing & roof

While we’ve been busy with our projects on the weekends, there has been much going on during the week as well.

putting in the knee walls

Initially, we wanted to keep the tongue and groove of the roof exposed on the front side of the upstairs bedrooms and build knee walls on the back for storage. However, once the air vents and pipes were placed, we had to rethink which walls we were going to keep exposed on the second floor.

A visit from Dave’s folks

Although Dave’s parents have been avid blog followers, they haven’t had a chance to get down here to check the place out since construction began.  Fortunately, they were able to come down and spend Christmas with us and we brought them down on Boxing day to take a look around.

Categories: Follow the adventure as we build our log cabin | Tags: , , , , , | Leave a comment

closing in the deck…

Though our original plan was to have stairs coming off of the back deck on either side, after giving that idea more consideration, we decided we’d feel more secure having the entire deck closed in. Given that our bedroom opens out onto the deck, and the fact that there are bears and bobcats in the area, we thought we’d feel more more comfortable sleeping there knowing that no unwanted visitors would be coming up onto the deck at night. However, as our blue prints showed an opening where the stairs were meant to be, our supply kit didn’t contain enough rails to close the deck in and the building crew had to leave the deck open on each end. Fortunately, there was enough lumber remaining after they finished up, as well as plenty of extra posts, that Dave was able to make the rails himself and we were able to close in the deck with no problem.

We were also very happy this week to receive a message from Todd Hawkes that his plumber had made it out to the cabin and began roughing in the plumbing.  Hooray, we’re that much closer to having indoor plumbing!!!

Categories: Follow the adventure as we build our log cabin | Tags: , , , , | Leave a comment

putting on the door knobs during the ice storm…good times….

And what did we do during the ice storm last Sunday? Drove down to the lake to put door knobs and locks on our cabin doors.  Yep, freezing rain, 29 degrees inside and out,  and only a puny little heater, hooked up to the generator, that barely put out any heat. Not sure how Dave managed to work with no gloves or coat as I was bundled up in my heavy parka with snow gloves on, standing in front of the little heater, and had numb fingers and toes within the first hour. We were met with one issue after another- having to re-drill holes to match the knobs and bolts, losing the teeny, tiny screw that held the handle to the rest of the fixture for the front door, and finding that the downstairs french doors weren’t hung straight so the predrilled holes for the door handles and strike plates were so far off that they couldn’t be adjusted to fit. It was a rather frustrating day but we were at least able to successfully get the locks and knobs on the upstairs doors and the side door in the basement.

Categories: Follow the adventure as we build our log cabin | Tags: , , | 1 Comment

christening the cabin…

27 years ago, while living in Zimbabwe, my dad took the old French tradition of Sabrage and altered it by using a large Ethiopian Danakil knife to open a bottle of champagne, rather than a saber.  It has become a family tradition ever since, although, since we don’t all own Danakil knives, we have found that a machete works just as well!  We never miss an opportunity to carry on the tradition, so in true form, we all drove down to the cabin the day after Thanksgiving to give our new place a true Richardson style christening! My brother Jason generally gets the honor of opening the bottle when we’re all together, mostly because he’s had the most practice. 😉

“There are many stories about this tradition. One of the more spirited tales is that of Madame Cliquot, who had inherited her husband’s small Champagne house at the age of 27. She used to entertain Napoleon’s officers in her vineyard, and as they rode off in the early morning with their complimentary bottle of Champagne, they would open it with their sabre to impress the rich young widow.” (http://en.wikipedia.org/wiki/Sabrage)

Categories: Fun times at Colemans Lake | Tags: , , , | Leave a comment

Blog at WordPress.com.